BUILDING PROGRESS – COLOR!

OCTOBER 27 2019

Our new Administration and Education building is on schedule for completion by Wednesday 18 December and we are on budget. The building has a roof, including seven heating, ventilation, air conditioning units.  The exterior walls have been wrapped in weather-proof material, insulated and two coats of man-made stucco have been applied.  The overwhelming majority of interior ductwork and interior insulation has been installed and the electrical, plumbing and low voltage wiring is over 90% complete.  As many of you saw with your own eyes during the walking tour on Sunday 27 October – progress is tangible and we are excited.  The Building Committee is very thankful for the encouragement, love, prayers, good will and support from the Congregation helping us make your dreams come true.  The next tour is scheduled for Sunday 24 November – we hope to see you all there.